Road and lane closures in the W3 area likely to lead to traffic problems
The following roadworks are likely to cause some delays in the Acton area:
Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer
A4000,A4020 High Street, Acton |
01 April — 04 April |
Delays likely Traffic control (two-way signals) |
Works description: 4x25mm B/P (CONX)for new water meter in fw and in Carriageway. Ourintention is to complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000806350490095-001 |
|
A4000,A40 Western Avenue, Acton |
03 April — 04 April |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368267 |
|
A4000,A40 Western Avenue, Acton |
03 April — 04 April |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368268 |
|
B4491,A4000 Gunnersbury Lane, Acton |
01 April — 03 April |
Delays likely Traffic control (two-way signals) |
Works description: Chamber Adjust Med Frame & Cover Cway in Carriageway. Ourintention is to complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031228619-001 |
|
Churchfield Road, Acton |
01 April — 09 April |
Delays likely Traffic control (two-way signals) |
Works description: LAY NEW SERVICE FROM MAIN IN FARSIDE CARRIAGEWAY |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000813823 |
A4000,A40 Western Avenue, Acton |
04 April — 05 April |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368272 |
|
A4000,A40 Western Avenue, Acton |
04 April — 05 April |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368273 |
|
|
B4491 Popes Lane, Ealing |
18 March — 24 May |
Delays likely Traffic control (multi-way signals) |
Works description: EXCAVATE TRENCH INSTALL CABLE CARRY OUT JOINTING BACKFILL AND REINSTATE |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP705S30001052 |
|
A4000,A40 Western Avenue, Acton |
18 March — 28 September |
Delays likely Road closure |
Works description: IPP Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG432331357 |
|
Westway |
18 March — 18 November |
Delays likely Road closure |
Works description: IPP Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432368104 |
|
Westway |
18 March — 18 November |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432366318 |
|
Friars Place Lane, Acton |
18 February — 04 April |
Delays likely Road closure |
Works description: IMGA192353. Replace approximately 400m of 600mm Medium Pressure SteelGas Main with new Plastic main. Including 2 connections and 2 excavations for bond and bolt camera surveys. |
Responsibility for works: Cadent |
Current status: Advanced planning |
Works reference: AZ0071000772458 |
Westway, Hammersmith and Fulham |
27 February — 22 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342350 |
|
A4000, A40 Western Avenue, Acton |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342348 |
A4000,A40 Western Avenue, Acton |
28 January — 29 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432329945 |
|
Westway |
28 January — 29 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432329946 |
|
April 2, 2019
|