The following roadworks are likely to cause some delays in the Acton area:

Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer

Roadworks in Acton

Friars Place Lane, Acton

18 February — 04 April

Delays likely Road closure

Works description: IMGA192353. Replace approximately 400m of 600mm Medium Pressure SteelGas Main with new Plastic main. Including 2 connections and 2 excavations for bond and bolt camera surveys.

Responsibility for works: Cadent

Current status: Advanced planning

Works reference: AZ0071000772458

A4000 Horn Lane, Acton

15 February — 28 February

Delays likely Lane closure

Works description: IMGA192469 LANE CLOSURE/TM PERMIT ONLY FOR ASSOCIATED WORKS INWESTERNAVENUE

Responsibility for works: Cadent

Current status: Planned work about to start

Works reference: AZ0071000805616

A4000 Victoria Road, Acton

15 February — 28 February

Delays likely Lane closure

Works description: IMGA192469 ABANDON 93M X 6" CI MAIN AND INSERT 90/125MM PE AND RELAYORTRANSFER SERVICES.

Responsibility for works: Cadent

Current status: Planned work about to start

Works reference: AZ0071000805614

A4000,A40 Western Avenue, Acton

28 January — 29 September

Delays likely Road closure

Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432329945

Westway

28 January — 29 September

Delays likely Road closure

Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432329946

A406 Gunnersbury Avenue (North Circular Road)

21 January — 19 March

Delays likely Contra-flow

Works description: Phase 1a - 1f Utility works, drainage and re-profiling works.

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG432343386

A406 Gunnersbury Avenue (North Circular Road)

07 January — 05 March

Delays likely Lane closure

Works description: Phase 1a - 2c Utility works, drainage and re-profiling works.

Responsibility for works: Transport for London

Current status: Advanced planning

Works reference: YG432343386

 