Road and lane closures in the W3 area likely to lead to traffic problems
The following roadworks are likely to cause some delays in the Acton area:
Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer
Friars Place Lane, Acton |
18 February — 04 April |
Delays likely Road closure |
Works description: IMGA192353. Replace approximately 400m of 600mm Medium Pressure SteelGas Main with new Plastic main. Including 2 connections and 2 excavations for bond and bolt camera surveys. |
Responsibility for works: Cadent |
Current status: Advanced planning |
Works reference: AZ0071000772458 |
A4000 Horn Lane, Acton |
15 February — 28 February |
Delays likely Lane closure |
Works description: IMGA192469 LANE CLOSURE/TM PERMIT ONLY FOR ASSOCIATED WORKS INWESTERNAVENUE |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000805616 |
|
A4000 Victoria Road, Acton |
15 February — 28 February |
Delays likely Lane closure |
Works description: IMGA192469 ABANDON 93M X 6" CI MAIN AND INSERT 90/125MM PE AND RELAYORTRANSFER SERVICES. |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000805614 |
|
A4000,A40 Western Avenue, Acton |
28 January — 29 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432329945 |
|
Westway |
28 January — 29 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432329946 |
|
A406 Gunnersbury Avenue (North Circular Road) |
21 January — 19 March |
Delays likely Contra-flow |
Works description: Phase 1a - 1f Utility works, drainage and re-profiling works. |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG432343386 |
A406 Gunnersbury Avenue (North Circular Road) |
07 January — 05 March |
Delays likely Lane closure |
Works description: Phase 1a - 2c Utility works, drainage and re-profiling works. |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432343386 |