Road and lane closures in the W3 area likely to lead to traffic problems
The following roadworks are likely to cause some delays in the Acton area:
Gunnersbury Avenue to Fully Reopen Later This Month
More closures likely next year for work on the North Circular
A4000,A40 Western Avenue, Acton |
27 August — 14 November |
Delays likely Lane closure |
Works description: IMGA182036. ABANDON 461M X 8" CI / SI MAIN ANDINSERT457MX180MMPEANDRELAYOR TRANSFER SERVICES. |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000742058 |
|
B408 Askew Road |
15 November — 17 November |
Delays likely Traffic control (Stop/Go boards) |
Works description: Electric duct to be dug across FW & Pipework to be connected inside chamber in C/W |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU895MGJV/FLIPS/202959 |
Kathleen Avenue, Acton |
20 August — 07 December |
Delays likely Road closure |
Works description: IMGA182032 - PERMIT FOR TM PURPOSES |
Responsibility for works: Cadent |
Current status: Advanced planning |
Works reference: AZ0071000721210 |
|
A4000,A40 Western Avenue, Acton |
20 July — 19 November |
Delays likely Lane closure |
Works location: A4000,A40 |
Works description: EXCAVATE AND RENEW EXSISTING LV CABLES / SERVICES TRANSFER ALL TO NEW MAINS BACKFILL AND REINSTATE |
Responsibility for works: SCOTTISH AND SOUTHERN POWER DISTRIBUTION |
Current status: Advanced planning |
Works reference: LP705S30000466 |
Gunnersbury Avenue (North Circular Road) |
7 Jun 2017 - 16 Nov 2018 |
Delays likely Lane Closure |
Works description:1 northbound lane closed, one running lane maintained northbound and two southbound. Traffic lanes will be realigned on the carriageway to suit phases of work during demolition of the main bridge. Lanes will first be slewed to the east and then to the west. |
Responsibility for works: Transport For London |
Current status: Work in progress |
November 13, 2018
|